The Task Progress Chart shows how a project's work has grown and been completed over time. It's a widget on the project's Summary view: click Summary at the top of the project.

Read the chart
The chart has two lines, each a running total over time:
- Total Tasks (grey) counts the tasks in the project, on the day each one was created.
- Completed (green) counts the completed tasks, on the day each one was completed.
The gap between the lines is the work still to do. As a project nears its end, the lines should come together: when they meet, every task is complete. A grey line that keeps rising means work is still being added.
Hover over the chart to see both totals for a day. To look at a shorter period, drag across the chart, then click Reset zoom to see the whole project again. The time axis always covers at least 14 days, so a new project's chart isn't squeezed into a few days.
What it counts
- Every task in the project counts, subtasks included.
- A task counts as completed when it has a status that completes it, such as Complete. If it's reopened, it drops out of the green line until it's completed again. See custom task statuses.
- The chart is worked out from the tasks in the project now. Deleted tasks, and tasks moved to another project, drop out of both lines for the whole history. A task moved into the project counts from the day it was first created.
- Days follow your own time zone.
The chart is only on project Summary views, not on My Tasks. If a project has no tasks yet, it shows "Add tasks to see task progress".
Rename or add the widget
The chart is a widget. To rename it, click the gear at the top right of the widget, choose Widget Settings, change the Title and click Save. The same menu has Remove.
To add it to a Summary view that doesn't have it, click Add Widget and choose it from the gallery. For status counts, the Task Summary widget shows how many tasks are in each status. For more detail on tasks, hours and dates, run the Task List report.