Yes. Instead of the default Not Started, In Progress and Complete, you can use your own statuses, such as Idea, Copy, Editing, Pending Approval and Published. Statuses belong to a task type, so each type can follow its own workflow.

A new Avaza account starts with one type, Task, with the three default statuses. Only Administrators can change statuses, in Settings › Project Management Settings.

Add or change a status

  1. Go to Settings › Project Management Settings. Under Task Types, click the type you want to change.

  2. In Task Type Details, click Add Task Status.

  3. Enter a Status Name, a Status Code and a Color. Tick is a Complete state if tasks in this status count as done.

  4. Click Save.

  5. Use Up and Down in the Order column to put the statuses in order.

To change a status later, click it in the Task Statuses table to open Status Details.

What each setting does

  • Status Name is what people see in the app and in reports. It can be up to 50 characters, and each status of a type needs its own name.
  • Status Code is a name for developers making API calls. Use letters and numbers only, up to 15 characters. You can't change it once it's saved.
  • Color marks the status on task icons, boards and summaries. Pick a clearly different colour for each status.
  • is a Complete state marks the statuses whose tasks are done. Filters such as All outstanding hide these tasks, and moving a task into a Complete status records its completed date. Every type needs at least one Complete status.
  • Allowed Destination Statuses (in Status Details) sets which statuses a task can move to next. The table shows it as Next Status can be. Leave it empty to allow any status. When it's set, a task's status menu offers only the allowed statuses, and a move that breaks the rule, such as a drag on a board, is refused.
  • Order sets the order of statuses in dropdowns, and in grouped lists, boards and reports.

The three stages

Every status belongs to one of three stages:

  • Not Started: only the built-in Not Started status. You can change its name, colour and allowed destination statuses. It always stays first, it can't be a Complete status, and it can't be deleted.
  • In Progress: every status without is a Complete state ticked.
  • Complete: every status with is a Complete state ticked.
The Task Summary on a project's Summary view: 8 tasks Not Started, 3 In Progress and 5 Complete, each count in its status colour

The Task Summary on a project's Summary view counts the tasks in each status. The Task List report can filter and group tasks by status.

Delete a status

Open the status and click Delete. Avaza won't delete:

  • Not Started.
  • A status that tasks still use, including tasks in archived projects. Move those tasks to another status first.
  • The type's last Complete status.

Deleting a status also removes it from other statuses' Allowed Destination Statuses.

For example workflows, such as a Development type with Design, Develop, Test, Deploy and Done, see task types.