A dependency links two tasks in the same project, so that one task waits on the other. For example, Build can start right after Design finishes.

Dependencies help you in three ways:

  • When a task's dates change, Avaza moves the tasks that wait on it.
  • You can see which tasks are waiting, which are ready to start and which hold others up.
  • The Gantt shows the links, and the tasks that set the project's finish date.
A project's Gantt with dependencies: the task list with each task's dates, assignee and % done, and on the chart each task's name under its bar and its assignee's initials after it, bars coloured by status, lines from each task to the tasks that wait on it, two milestones as diamonds, each section's bar with its progress, and gap labels reading after it starts and +1 day

How a dependency works

Every dependency has a task that waits and a task it waits on. Avaza writes each dependency as a sentence. There are four kinds:

Kind

How Avaza writes it

Finish to start (the most common)

Build can start right after Design finishes.

Start to start

Test can start right after Build starts.

Finish to finish

Docs can finish right after Build finishes.

Start to finish

Handover can finish right after Support starts.

A dependency can also have a gap. For example, Build can start 2 working days after Design finishes. The gap counts working days, or calendar days if you choose calendar days. A gap can also go the other way, so that a task can start a few working days before the other finishes. A gap can be up to 260 days.

Working days are your account's working week and public holidays. You set both on the Team Schedule settings page.

A task with dependencies shows one of these states:

  • Waiting: a task it waits on hasn't finished. For a start-to-start dependency, the other task hasn't started.
  • Blocking: other tasks are waiting on this one.
  • Ready to start: nothing it waits on holds it up any more, and the task hasn't started.

Finish-to-finish and start-to-finish dependencies never make a task wait. They only affect its dates.

The rules

  • Both tasks must be in the same project.
  • A task can't wait on itself, on its parent task or on its own subtask.
  • Two tasks can only be linked once.
  • A dependency can't make a loop. If Test waits on Build, Build can't also wait on Test.

To add, change or remove dependencies, you need the Update task permission on the project. See project settings.

Add a dependency in a task

  1. Open the task and click the Dependencies tab. It's the tab after Subtasks, and its number counts the task's dependencies.

    A task's Dependencies tab: Milestone and Lock dates switches at the top, then three tasks under Waiting on and one under Blocking, each with its section, status, assignee and dates and the dependency in words, such as Starts right after it finishes, and an Add task button by each list
  2. Click Add task. Use the one under Waiting on for a task this one waits on, or the one under Blocking for a task that waits on this one.

  3. Search for the other task. The list shows this project's tasks. Tasks that fit best come first, marked Finishes before this starts or Starts after this finishes. Tasks you can't pick are greyed out, with the reason.

    Add a task this one waits on, open under Waiting on: a search box, then the project's tasks with their section, status and dates, the best fits marked Finishes before this starts
  4. Check the When, Then and Timing rows. Change the kind of dependency or add a gap if you need to. Under them, a sentence says what the dependency means and whether the task would move.

  5. Click Add. If other tasks would move, a ticked box says how many, for example Move 2 tasks to keep this order. To keep every other date, untick it first.

The Dependencies tab has two lists: Waiting on and Blocking. Each row shows the other task's section, status, assignees and dates, and the dependency in a few words, such as Starts right after it finishes. Click those words to change it. Click × to remove the dependency. Avaza doesn't ask first, so a message offers Undo instead.

When a task is waiting, a blue line under its title says so on every tab, for example Waiting on Design. The line turns red when a task it waits on is late, and says since when. If the task only holds others up, the line is grey and says how many are waiting on it. Click the line to open the Dependencies tab. Open in Gantt shows the task on the project's Gantt.

Add dependencies on the Gantt

Point at a bar on the Gantt and a dot appears at each end. Drag from a dot to an end of another bar. If that bar is off screen, drag towards the edge and the chart scrolls. The ends you use set the kind of dependency. For example, drag from the end of Design to the start of Build for "Build can start right after Design finishes".

If the new dependency would move other tasks or leave a conflict, and the project asks first, a box opens next to the bar. It puts the dependency into words and lists the tasks that would move, with their old and new dates, and the chart shows where they would go. Choose Add and move 2 tasks (with the number of tasks), Add, don't move or Cancel. Enter adds, and Esc cancels. After the dependency is added, a message offers Undo. On a phone, the same choices appear in a bar under the chart.

A box next to a bar on the Gantt asking Add dependency?: Client review can start right after Copywriting finishes, the 6 tasks that would move later with their old and new dates, a warning that a task with locked dates would start too early, and the buttons Cancel, Add, don't move and Add and move 6 tasks
  • See a dependency: point at its line. A card shows the two tasks in order, with their dates and how they're linked.
  • Change or remove it: click the line. Edit dependency opens with the same When, Then and Timing rows. Change them and click Save, or click Remove. If other tasks would move, untick Move 2 tasks to keep this order to save without moving them.
  • Link several tasks in a row: select them with Ctrl or Shift, right-click and choose Link 3 tasks in order (the number follows your selection). Each task then waits on the one above it.

Dependencies don't show when the Gantt is grouped by Assigned To.

What happens when dates change

When a task's dates change, the tasks that wait on it can move too. This works when you change the dates in the task, on the Gantt, on the Calendar or with Shift dates. It also works when you drag a booking on the Team Schedule.

Each project chooses what happens, in Project Settings › Dependencies:

  • Move with it, keeping the gaps (the default): waiting tasks move by the same number of working days.
  • Only move to avoid overlap: waiting tasks move only when they would start too early. They never move earlier.
  • Don't move, just show conflicts: nothing else moves. A dependency that no longer works shows in red.

Administrators can set what new projects start with, in Settings › Project Management Settings › Task Dependencies. Existing projects don't change, and each project can still choose for itself.

Project Settings on the Dependencies page: the three ways tasks move, Ask before moving other tasks ticked, and the two choices for completing a task that's still waiting

With Ask before moving other tasks ticked (the default), Avaza shows what will move before it saves. It lists each task with its old and new dates, and the project's new finish date. Then choose:

  • Move 2 tasks (with the number of tasks): save the change and move the waiting tasks.
  • Only change this task: save the change and move nothing else.
  • Cancel: change nothing.
A task moved one working day later on the Gantt: its old place and the old places of the tasks that wait on it shown dashed, their new places outlined in blue, and the bar under the chart asking Move the 6 tasks that depend on this? with each task's old and new dates, a warning with Unlock and move, and the buttons Cancel, Only change this task and Move 6 tasks

Tick Don't ask me again on this project to skip this step for yourself. To be asked again, open Project Settings › Dependencies and click Ask me again.

After a change, a message shows what moved, with Undo. The message stays for 10 seconds, and longer while you point at it. You can also undo a change later from the task's History tab, for 30 days.

Tasks that never move

Avaza doesn't move a task that waits on another when:

  • the task is done;
  • its dates are locked;
  • it has already started;
  • it's linked to a recurring booking on the Team Schedule;
  • you can't edit it.

If such a task now starts too early, its dependency shows in red as a conflict. Where there's a fix, Avaza offers it, such as Move to a date or Unlock and move. Otherwise it says why the task can't move.

A task that has already started can't change its start. If it started too early but its due date is still late enough, its dependency shows in amber. If its due date is too early as well, the dependency shows in red, and the fix is Move its due date. If its dates are also locked, the fix is Unlock and move its due date.

Tasks that move keep their length in working days, and start on a working day. Subtasks move with their parent task. Bookings on the Team Schedule move with their tasks. If a person would then be booked for more hours than they have, Avaza warns you before it saves.

Milestones and locked dates

At the top of the Dependencies tab:

  • Milestone turns the task into a one-day milestone, shown as a diamond on the Gantt on its due date. A ◆ shows before its title.
  • Lock dates stops other tasks from moving this task. You can still change its dates yourself. A lock shows next to the dates.

A task needs a start or due date before you can lock its dates.

Completing and starting tasks

Each project also chooses what happens when someone completes a task that's still waiting. The setting is Completing a task that's still waiting, in Project Settings › Dependencies:

  • Warn but allow (the default): Avaza asks first. Choose Keep it open or Complete anyway.
  • Don't allow: the task can't be completed until the tasks it waits on are finished.

This applies everywhere you complete a task, including the status menus in lists and dropping a card on the Board.

You can start a waiting task early. The task's popup then shows a note under its status, for example Started while still waiting on Design.

When a task with waiting tasks is completed late or early, Avaza offers to move the tasks after it by the same number of working days. Choose Move 2 tasks (with the number of tasks) or Not now. If you move them, the completed task's due date also changes to the day it was finished.

See dependencies in lists and on the Board

The Dependencies field shows short labels on each task:

  • Conflict: this task's dates break a dependency. It reads 2 conflicts when more than one does.
  • Waiting on 2: the number of tasks it's waiting on.
  • Waiting on a late task
  • Blocking 3: the number of tasks waiting on this one.
  • Ready to start

Point at a label to see the tasks. The field shows on Board cards. In a list or on a Gantt, add it with Fields. See custom views.

Board cards with their dependency labels, such as Waiting on 1, Waiting on 3 and Blocking 2

On Project Tasks and My Tasks you can also filter by Waiting, Ready to start, Blocking others, Milestone and Dates locked. The Waiting quick filter shows only waiting tasks. Sort by Dependencies to put the tasks that wait on the most tasks first.

Change several tasks at once

On Project Tasks, in the List view, tick the tasks you want to change:

  • Tick a section's box to choose all of its tasks, even when the section is collapsed.
  • Hold Shift as you tick to choose the tasks in between.
  • Hold Ctrl (Cmd on a Mac) and click a task to add it.
  • Press Ctrl+A (Cmd+A), or click Select all in the bar, to choose every task on screen. Tasks in a collapsed section aren't included.
  • On a phone, press and hold a task to start, then tap the others.
  • Press Esc to clear the selection.

A bar appears at the bottom of the list:

  • Status: set the tasks to a status of their task type. Tasks of different types can't be changed together. A task whose status workflow doesn't allow the change is left as it is.
  • Assignee: make one person the only assignee, or add or remove a person.
  • Due date: give the tasks the same due date, or clear it. Completed tasks, and tasks that start after the new due date, are left as they are.
  • Priority and Tags: set a priority, or add and remove the project's tags.
  • Move to: move the tasks to another section, or to another project. When they move to another project, people who aren't members of it come off the tasks, dependencies with tasks staying behind are removed, and the tasks lose their tags (tags belong to a project). Avaza lists all of this before you confirm. This can't be undone.
  • More: Shift dates (move the tasks later or earlier by a number of working days, or choose the date the first one starts; it lists each task's old and new dates first), Link in order (make each task wait on the one above it; use the arrows to change the order before you add them), Lock dates, Unlock dates or Delete.

Each option shows how many tasks it will change before you confirm. You can change up to 200 tasks at a time. Afterwards a message says what changed, and Why? lists the tasks that were left as they were, with the reason. Changes made with Due date, Shift dates, Link in order, Lock dates and Unlock dates can be undone from that message.

To move a whole section, open the section's menu and choose Shift this section. To move the whole project, choose Shift project dates in the project's ⋮ menu. Shift dates shows what will move before it saves, and leaves tasks that are done or started where they are. Tasks you chose shift even when their dates are locked; Shift this section and Shift project dates leave locked tasks where they are.

To add the next task in a chain, open a task's menu in the list and choose Add task after. The new task waits on that task and starts when that task finishes.

Plan on the Gantt

The Gantt has more tools for planning:

  • Critical path: shows the tasks that set the project's finish date. Any delay to them moves the finish date.
  • Hide weekends: hides weekends and holidays from the timeline. Dragging a bar then moves it by working days.
  • Today: brings today into view. Pressing T does the same.
  • Zoom: from 5 years to Week, with Fit project to show every task at once. Ctrl and the mouse wheel zoom too.
  • Unscheduled: tasks without dates are listed at the bottom. Point at a task's row on the timeline, then click a day to schedule it, or drag to set a range. It lands on working days, so a click on a Saturday schedules the Monday. On a touch screen, drag its Assign dates target instead.
  • Start and End columns: click a date to change it. Type a date such as "5 Nov", or pick one from the calendar. Changing the start moves the whole task.
  • Right-click a bar or a row for Shift dates, Add task after and Lock dates.
  • Off-screen tasks: when a task's bar is off screen, an arrow on its row points the way. Click it to go to the bar.
  • Section progress: when tasks are grouped by section, each section's bar shows how much of it is done, weighted by working days. Avaza works this out from the section's tasks, so you can't edit it.
  • Duration and Status columns: tick them in Fields, on a project's Gantt or My Tasks. Duration is the task's length in working days. Click it and type a number: the start stays and the end follows, or with no start, the end stays and the start is worked out. It works like changing the End date, so tasks that wait on it can move too. You can't change it for a milestone or a task with no dates. Status shows the task's status.
  • Task list: the round button on the edge of the list hides and shows it. The columns icon in its header opens Manage Columns, the same as Fields.

On the Gantt you can group tasks by Section or by Assigned To, and sort them by Manual Sort or Start Date. You can also use the Gantt with a keyboard, or on a tablet. On a tablet, tap a bar before you drag it, and press and hold for its menu.

Notifications

Avaza sends three notifications about dependencies:

  • You're no longer waiting: the last task your task was waiting on is finished.
  • Your tasks were moved: a change to another task moved your tasks.
  • Completed while still waiting: a task was completed while it was still waiting on your task. The completed task's followers get this one too.

The first two go to the people assigned to the task. Nobody is notified about their own changes. To choose how you get them, open Notification Settings. See notification settings.

Other things to know

  • Moving a task to another project: dependencies only work within one project. If the task has dependencies, Avaza asks you to remove them first. Choose Remove and move. See moving tasks between projects.
  • Subtasks: a task can't go under a task it's linked to. Remove the dependency first. See subtasks.
  • Copying: copying a project, or creating one from a template, copies the dependencies between its tasks. Duplicating a single task doesn't copy its dependencies.
  • Importing tasks: the task import has a Predecessors column. Enter the RowIDs of the rows a task waits on, for example 3, or 3:SS for start to start. See importing data.
  • Reports: the Task List report can show Milestone, Dates Locked, Waiting, Waiting On and Blocking columns. See the Task List report.
  • History: each task's History tab lists the dependencies added, changed and removed, and the dates they moved.